A deadline is counted in working days, not in calendar days. NETWORKDAYS counts the working days between two dates, and WORKDAY finds the date reached after a number of working days. Both functions remove weekends, and they can also remove public holidays.
The following exercise shows you how to plan dates with NETWORKDAYS and WORKDAY.
What you will practice in this exercise
You work on a planning table with a list of public holidays. You answer 6 questions, one formula per question:
- Working days in the first quarter (NETWORKDAYS)
- Same count without public holidays (holiday list)
- Working days from a hire date to a reference date
- Date after 20 working days (WORKDAY)
- Same date without public holidays (WORKDAY + holidays)
- Date after 30 working days from a given date
Practice with exercises
NETWORKDAYS — Scheduling
Count actual working days, excluding weekends and public holidays.